| Following termination of uranium mining, activities
at the Ronneburg site in East Thuringia switched to mine decommissioning
and close-out, just as at any other mining or milling site operated
by SDAG Wismut. Approximately 27 million cubic metres of open mine workings
and 40 shafts had to be prepared for flooding. This involved removal
of grease/oils and of hazardous chemicals from underground mines, backfilling
and sealing of day shafts and near-surface mine voids, and construction
of about 120 hydraulic barriers.
Flooding of mine workings occurs in two hydraulically separate systems:
flooding of the mine fields located south of the A 4 motorway was initiated
at the turn of the year 1997/98, that of the mine fields located north
of the
|